The vision of an Alpine crossing takes shape

Ropeway station on a snowy mountain peak under a clear blue sky.
Zermatt, 28 May 2020

For the armies of Hannibal and Napoleon, crossing the Alps was a trailblazing endeavour. Later, their lead was followed by the aviation pioneer Geo Chavez, who became the first person to fly over the Alps. And the pioneering spirit is alive and well today in Zermatt: with Project X (Alpine Crossing), Zermatt Bergbahnen AG has laid the foundation stone for the highest ropeway crossing of the Alps, running between Zermatt in Switzerland and Cervinia in Italy.

The first connection between Breuil-Cervinia and Zermatt was created in 1939 with the opening of the cable car from Plan Maison to Plateau Rosa. From there, winter sports enthusiasts coming from Italy could reach the slopes on the Zermatt side of the border. In the decades that followed, several ropeways were also built on the Swiss side, culminating in the completion of the link between Zermatt and the Klein Matterhorn in 1979. The next milestone was achieved two years ago when the Matterhorn glacier ride I opened to the public. Now, as construction work scheduled for the next two summers gets under way on the Matterhorn glacier ride II, a structurally similar tricable gondola lift

between Testa Grigia and the Klein Matterhorn, the final remaining gap between Zermatt and Breuil- Cervinia is set to be closed. When the Matterhorn glacier ride II opens in readiness for the 2021/22 winter season, the highest crossing of the Alps by ropeway will become a reality.

Zermatt Bergbahnen AG has not been immune to the effects of the lockdown, which has caused uncertainty across the entire tourist industry. However, rather than falling into a state of paralysis, Zermatt Bergbahnen AG has been setting its sights on life after the pandemic. The initial position may be more difficult but thanks to its sound financial situation ZBAG is going ahead with its major investments as planned and will continue with the construction of the Matterhorn glacier ride II, with an estimated budget of 35 million Swiss francs. Due to the quick installation of safety measures at the construction sites, work could already start again this spring, albeit on a reduced scale.

According to Franz Julen, Chairman of the Board of ZBAG: “The Matterhorn glacier ride II and with it the Alpine X, the all-year connection between Zermatt and Italy, will present ZBAG, the Zermatt-Matterhorn resort and the Valle d’Aosta with many opportunities and provide a boost for the tourist sector both in the winter and especially the summer. For many years, Zermatt has stood for pioneering spirit, entrepreneurship, a belief in tourism and in the future, but also for respect and humility in the face of nature. The Matterhorn glacier rides I and II, along with the associated infrastructure and services on the Klein Matterhorn, will form the next chapter in Zermatt’s success story.”

Custom technology the key to success

The installation of a tricable gondola lift in a location where space is severely restricted and at altitudes of over 3800 metres above sea level not only requires the highest levels of precision from the construction workers but also presents the ropeway engineers at LEITNER ropeways with huge challenges. For example, the construction of the Matterhorn glacier ride II requires a custom solution specially built to cope with the difficult conditions. Thanks to the increased wind stability of the 3S system, it is possible to construct the 1.7-kilometre span between the two stations entirely without the need for supporting towers.

Other technical innovations will be evident in the mountain station. Drive power will be provided by two high-performance DirectDrive synchronous motors working independently of each other. Leitner’s DirectDrive system operates without gears and connects directly to the pulley wheel, reducing maintenance, wear and energy consumption to a minimum. In combination with the use of supplementary emergency and rescue drive systems, this redundant system ensures that in the event of an emergency passengers can always be brought back to the stations. The gondola lift has four separate drive types which can all be powered independently of each other via the electricity supply network or an emergency power supply.

Because of the limitations on space on the mountain, a shorter than usual drive station is being built. The station will allow cabins to enter and leave with a cable speed of 5 metres per second. The cabins can be braked or accelerated before they reach the station. The shorter drive station means that the energy requirement in the mountain station can be reduced.

The third new feature in the mountain station will be a system of rails that make it possible for the cabins to be swapped between the two sections, so the cabins from the MGR II section can be mounted onto the MGR I cable and brought to the big station hall at Trockener Steg for inspection there. The capacity to keep all the cabins from both sections at Trockener Steg and garage the ten cabins from the Matterhorn glacier ride II in the loop of both systems will save a great deal of space in the station buildings.

Individuality in all things

In terms of design and finishing, LEITNER ropeways is satisfying Zermatt Bergbahnen AG’s every wish. For example, passengers will have the pleasure of travelling in cabins designed by Pininfarina, sitting on heated leather seats and enjoying the views of the surrounding alpine landscape through panoramic windows. Anyone in search of luxury and excitement can book into one of the Crystal Ride cabins for the section between Testa Grigia and the Klein Matterhorn. The journey will be an experience to remember, thanks to the glittering Swarovski crystals and a glass floor that reveals views of the glacier below.

To give an idea of the Alpine X vision, LEITNER ropeways and Zermatt Bergbahnen AG have jointly produced a video of the project. For the film, photogrammetric measurements of the Klein Matterhorn and Testa Grigia were carried out using a drone. The impressive video was edited together from a mixture of drone images, 360° video recordings of the route of the ropeway and 3D animations. It was only possible to overcome the challenge of filming at this altitude thanks to the expertise of our partners at LEITNER ropeways. The results speak for themselves and can be viewed at www.matterhornparadise.ch/en/AlpineX. Immerse yourself in the Alpine X – or rather, take off and enjoy the flight over the Alps.

Matterhorn glacier ride II: technical details

HIGH VALLEY STATION SPEED 3458 m above sea level 7.5 m/sec

HIGH MOUNTAIN STATION JOURNEY TIME 3821 m above sea level 4 min.

CABLE MANUFACTURER NUMBER OF CABINS LEITNER ropeways 10

CABLE LENGTH PASSENGERS PER CABIN 1.7 km 28

ELEVATION DIFFERENCE DRIVE SYSTEM 362 m LEITNER DirectDrive

CARRYING CAPACITY CABIN DESIGN 1300 passengers per hour Pininfarina For further information, please contact:

Mathias Imoberdorf Communication & Media Manager Zermatt Bergbahnen AG +41 (0)27 966 01 24 mathias.imoberdorf@zbag.ch

References

Discover the installation in detail

Matterhorn glacier ride

Zermatt – Switzerland – 2018

With the opening of the world's highest 3S gondola lift on the Klein Matterhorn on Sep­tember 29, 2018, several record-breaking facts have now been rolled into a single project. The four-kilometer journey to almost 4,000 meters above sea level leads to Europe's highest top station. The eight-kilometer long hauling rope weighs an impressive 67 tons and is freely suspended over a distance of three kilometers at the longest span of the system. For the first time in the history of LEITNER ropeways, thou­sands of Swarovski® crystal beads refine the exterior on four of the 25 cabins designed by Pininfarina and also decorate the lettering on the comfortable seats. Thanks to another tech­nical feature, these cabins offer a spectacular view during the nine-minute ride: After three minutes, at an altitude of 170 meters above ground, the cloudy glass floor clears up in seconds to provide guests with a magnificent view.

TD28

Ropeway type

2.000

Throughput per hour

7,5 m/s

Speed

Matterhorn Glacier Ride II

Zermatt – Switzerland – 2023

The Matterhorn Alpine Crossing is a unique, once-in a generation project which has created the highest border crossing in the Alps and connects two tourist destinations in Italy and Switzerland throughout the year. The construction of the new “Matterhorn Glacier Ride II” tricable gondola lift has closed the last remaining gap between Zermatt and Breuil-Cervinia, thus bringing to fruition a longheld vision. As well as its pioneering technical implementation, which includes bridging the distances between the top and bottom station on the “Matterhorn Glacier Ride II” without towers, much emphasis was placed on sustainability. For example, an additional photovoltaic system was commissioned on the facade of the new top station and will supply around 16,875 kWh of electricity each year. This project is unique in a number of ways. It involved pioneering work on the construction sites at extreme altitudes, as well as collaboration between two countries on a joint project which connects two tourism areas throughout the year.

TD28

Ropeway type

1.300

Throughput per hour

8,0 m/s

Speed

Press

Press area

The vision of an Alpine crossing takes shape

6 Downloads available


Related news

More interesting articles

ROPERA®: Digital Solutions for Efficient Ropeway Operations

19.11.2026

New Operations & Technology Hub

20.10.2026

LEITNER is setting new standards for the future of ropeways in Austria

02.07.2026

LEITNER’s first ROPERA® system in Switzerland is coming to Zermatt

23.06.2026

Above the traffic jams: LEITNER expands Mexico’s ropeway network by a furth...

09.06.2026

LEITNER inaugurates a new client training center in Ratschings

11.05.2026

LEITNER’s innovation push: ROPERA® impresses experts at Mountain Planet 202...

16.04.2026

Innovative Premiere: From 2027, the world’s first aerial tramway with Direc...

17.03.2026

LEITNER launches major technology initiative at Mountain Planet 2026

05.03.2026

LEITNER ropeways are setting new trends in many regions of Europe

20.02.2026

Download files

General Terms and Conditions

By using this content, you agree to the Terms of Use as well as to providing correct copyright attribution.

Download files

Download